Before one signs on the dotted line, the terms and conditions should be reviewed to ensure that these are acceptable. One’s ability to carry out an insightful review is dependent on the level of understanding of the clauses in hand. In the process of review, one is essentially examining whether the terms give rise to any risk and if so, can the risk be managed? There are usually various parties involved in reviewing any draft agreement including commercial manager and legal counsel. Rightly or wrongly, arbitration clause is often deemed a “legal matter” and therefore falls within the purview of the legal counsel as opposed to commercial manager. Whilst a legal counsel could advise whether a clause is “legally operable”, an effective commercial manager provides an additional perspective of whether it makes business sense to shoulder certain risk even if the clause is entirely operable or enforceable. Unfortunately when it comes to the subject of arbitration, it often give rise to the perception of being pure legal issue and in turn lacks a balance commercial scrutiny. This article therefore provides a basic understanding of arbitration clause and how it can be reviewed commercially. Indeed there are commercial dimensions to any arbitration clause that remain under appreciated.
What is Arbitration?
Typically parties in dispute commence their legal actions in a state court where a presiding judge would hear the merits of their arguments and make a judgment that is binding and legally enforceable on both parties. This dispute resolution process is known as ‘litigation’ and the proceedings are governed by the prevailing rules of the court. Arbitration is an alternative method of resolving dispute where the contesting parties are relatively in greater control over the process. Arbitration operates by consent of the parties where disputes are referred to arbitrator(s) instead of a judge. The rules of the arbitral proceedings including the appointment of arbitrator are based on parties’ choice and matters are heard in a private forum instead of a court. The outcome of an arbitration is an arbitral award in which the decisions are also legally binding on both parties.
Therefore the one distinctive element of an arbitration is the parties’ freedom or autonomy to dictate the manner in which their disputes will be resolved. This freedom can be an advantage if parties’ have a good understanding of the mechanism of arbitration and be able to negotiate an arbitration clause that make sense both legally and commercially. Any asymmetry of knowledge and expertise between the parties in respect of arbitration may have a profound financial implication down the road. This is because once parties include an arbitration clause in their contract, either party is not at liberty to revert back to the conventional court litigation without the consent of the counter party. The state court respects the parties’ decision to refer their disputes to arbitration and would not interfere under ordinary circumstances. There are also legislations in place in most jurisdictions that limits the state court’s ability to interfere with arbitral proceedings. The fact that an arbitration is conducted in a private forum does not make it less worthy in its legal force.
The scope within which the parties are free to stipulate their terms of arbitration can be identified from the wordings in their agreed arbitration clause. Arbitration clauses are included in standard form of construction contract and are usually found at the tail end of the contract form. Such clause usually include amongst others, the types of disputes that can be referred to arbitration, the number of arbitrator, the arbitration institutions and its rules that would govern the proceedings, when can the parties commence legal action, any condition precedent prior to the commencement of arbitration, the applicable arbitration law, the seat of arbitration etc. The breadth of issues in respect of an arbitration agreement that can be agreed upon by the parties are wide ranging.
Where Can The Outcome of Arbitration Be Enforced?
The outcome of an arbitration is often referred to as the ‘arbitral award’. This is the decision rendered by the arbitrator based on the issues that are within his scope of jurisdiction. An arbitral award is widely recognised which allows it to be enforced internationally in countries which are state parties of the New York Convention. To date there are 172 state parties globally under the New York Convention. By contrast, the judgment of a state court does not enjoy the same level of international enforceability as that of an arbitral award. Court judgment has a relatively limited international enforceability and are almost exclusive to countries with some form of reciprocal enforcement of foreign judgment arrangement. These reciprocal arrangements are often instituted either bilaterally or regionally. This limitation is due various reasons including amongst others the issue of sovereignty of nations, varying legal system with different legal principles and also certain matters are deemed national interest where foreign interference are not permissible. One of the ways in which New York Convention addresses some of those concerns is by establishing a common legislative standards. Through UNCITRAL Model Law, state parties have a better chance of being able to streamline their respective arbitration laws in harmony to one another. It also provides a legal framework in respect of the relationship between the state court and an arbitral tribunal. In supporting international arbitration, state parties agreed for a limited curial intervention against arbitral award except in rare instances of procedural error committed in the arbitral proceedings. This in turn provides certainty and trust in the arbitral proceeding in terms of the finality in dispute resolution. As compared to international arbitration, domestic arbitration face less cross border enforcement challenges in that both disputing parties are domiciled within the same jurisdiction.
The international enforceability of an arbitral award is an advantage when carrying out construction projects in a foreign country where legal risk is a significant consideration. This leads to the next section of this article on some of the reasons why arbitration is widely adopted.
Why Arbitration?
In an international transaction where the construction contract is between the Employer from Country A and the main contractor from Country B with the project being carried out in Country C, arbitration clause can be useful. Both Party A and Party B being foreign entities are unlikely to have much assets in Country C. Even if either party obtains a favourable judgment through the state court in Country C, it is unlikely to amount to much practically. Assuming there is no reciprocal of enforcement of foreign judgment arrangement between either countries A or B with C, the winning party will face an uphill task in securing the losing party’s assets. In this regard, an international arbitration clause helps resolve these cross border legal issues. This is an important commercial consideration before one decides whether to spend a considerable amount of legal costs to pursue any claim.
Even if both disputing parties and the location of the project are within the same jurisdiction, there are also merits to having an arbitration clause. This is because parties have considerable freedom and latitude to agree on the dispute resolution framework and structure. By way of example, parties may agree in advance to appoint certain arbitrator with technical background in construction dispute which could boost parties’ confidence in the dispute resolution process. Usually the litigants under a court system do not have the freedom to pick and choose their judges who will preside over their case.
One of the advantages to having an arbitration as a mode of dispute resolution is that is provides the disputing parties privacy. Some businesses may view getting embroiled in legal tussle as damaging to their reputation and brand. These businesses often avoid pursuing legal actions especially if they are actively bidding for projects for fear of being seen as being claims conscious or outright litigious. The arbitration rules are usually drafted with these concerns in mind. With parties’ mutual consent, arbitral proceedings incorporates privacy safeguards. Court system on the other hand upholds open justice principle where judicial proceedings are usually carried out in a transparent manner with much public scrutiny.
Any parties that ever get involved in disputes will acknowledge that once the relationship sours, the disputing parties could hardly ever agree on anything. The animosity can spread from the core issues to other peripheral issues which could have been easily agreed but for the underlying disputes. This makes it that much harder for disputing parties to ever negotiate or mediate their dispute. Any party that initiates such reconciliatory measures are concern of being seen as ‘weak’. To overcome this problem, certain arbitration clauses incorporate condition precedents as part of their tiered dispute resolution mechanism. This means that no parties are allowed to commence an arbitration, before attempting to resolve those disputes through either negotiation and/or mediation. These conditions precedents are usually well defined in terms of duration within which these needs to happen and certain written communications between parties to signify the formality of commencement of these condition precedents. This is to provide a mandatory pathway for parties to at least make the effort of negotiation or mediation without the party initiating being seen as weak. The flip side to these condition precedents is that if such measures are not adequately fulfilled, any reference to arbitration will be deemed premature and could compromise the jurisdiction or authority of the subsequent appointed arbitrator. Any multi tiered dispute resolution provision therefore can fundamentally affect the question of when can disputes be referred to arbitration. This issue will be examined in further detail in the next section of this article.
When Can Disputes Be Referred to Arbitration?
As alluded to earlier, the effect of any multi tiered dispute resolution mechanism meant that parties are not permitted to immediately refer any dispute to arbitration before first resorting to negotiation or mediation that may be specified as a condition precedent. Whilst these condition precedents opens up the possibility of reconciliation and parties’ control over the outcome of resolution of dispute, it can also be abused as a delaying tactic when either party does not have any genuine intention of settling their differences. Settlement of dispute usually require parties to compromise rather than finding fault. Some are cautious of making any compromise for fear of causing prejudice to their legal positions if negotiations or mediation subsequently fails. Occasionally the representatives of either disputing parties are not incentivised to settle expeditiously especially if their employment ceased upon the financial closure of the project. For all these possible scenarios, condition precedents may not necessarily assist with dispute resolutions.
Most standard forms of construction contracts provide for a certifier who can either be the architect, engineer, employer’s representative or others. This certifier is usually a named individual with certain powers provided for under the contract. Some conditions of contract would require that parties refer their disputes or differences firstly in writing to such certifier and the certifier will then be required to make a decision within a specified duration. The party that continue to be dissatisfied with that decision can then refer the certifier’s decision to arbitration. Whilst this may be seen as yet another time consuming condition precedent, there may be good reasons for such mechanism to be in place. One aspect of dispute resolution that is often gets overlooked is “crystallisation” of dispute. When one party is required to articulate their claims on a specific matter formally in writing, it forces one to be specific with its position. The other party will therefore be given a chance to counter with its specific position or to reject the claim with logic and reasons. This process when carried out with mental clarity allows the real dispute to crystallise and be itemised in a discrete manner. Even if one party is dissatisfied with the certifier’s decision, it allows issues subsequently referred to an arbitrator to be properly framed and defined.
There are also conditions of contract that prohibits any reference of dispute to arbitration until the project is substantially completed. It is fair to say that once parties in a construction contract commences legal action under arbitration, their relationship is severely compromised. At that point there is a real prospect of the project not being able to continue to the point of completion. Therefore arguably this condition precedent safeguards the Employer’s interest of at least being able to complete its project before dealing with any claims and dispute under arbitration. If the contractor has issues with the Employer involving progress payments and claims, there are statutory adjudications recourse available assuming there are legislations such as Security of Payments Act in place that aims to facilitate cashflow.
When disputing parties are finally able to refer their disputes to arbitration, it is crucial to understand the different points of contact, institutions or administrative parties and their respective roles that will facilitate the commencement of the arbitral proceedings.
Who are Relevant Parties Involved in An Arbitration Proceeding?
The party initiating the arbitration is usually referred to as the Claimant whilst the counter party is known as the Respondent. Apart from providing its defence, the latter occasionally makes its counter claim against the Claimant. The Tribunal refers to an arbitrator or a panel of arbitrators presiding over the proceedings and resolving or determining the disputes submitted by the parties. The number of arbitrator(s) is usually decided by the parties.
It is not uncommon for the parties to also dispute over interpretation of the arbitration clause including how many arbitrator to be appointed and the manner in which the Tribunal shall be constituted. Therefore it is often useful for the parties to agree on an institutional arbitration agreement as opposed to an ad hoc arbitration agreement. Under institutional arbitration agreement, the parties would have agreed upon a defined arbitration institution to administer the arbitral proceedings including a set of arbitration rules that governs the conduct of the proceedings from inception to completion. The absence of any agreed set of procedural rules before the Tribunal is constituted could give rise to a tricky legal terrain for any party to navigate. There are various arbitration institutions such as the International Chamber of Commerce (ICC), Singapore International Arbitration Centre (SIAC), London Court of International Arbitration (LCIA) etc. Ad hoc arbitration on the other hand, relies primarily on the arbitrator to set the rules as the parties at the stage of arbitration are unlikely to agree on much issues. Where parties had entered into standard form of construction contract, the arbitration clause included therein would typically provide for an institutional arbitration. Therefore the arbitration institution is an important component of dispute resolution mechanism for parties to be familiar with from the outset.
Within an arbitration institution, there is usually a Registrar or Secretariat as well as the Court within the institution. Generally, the Secretariat is the party that receives a request for arbitration from the Claimant. It plays an important administrative function prior to the constitution of the Tribunal in ensuring the parties submits the relevant information and documents as required under the arbitration rules including payment of any fees. The Court within the arbitration institution does not resolve the substantive disputes between the parties but plays an important role in making determinations as to whether the arbitration should proceed and hears challenges that either party may have on the authority of the Tribunal. Any decision made by the Court is usually without prejudice to the Tribunal’s subsequent authority to decide on its own jurisdiction should the Court decide that the arbitration shall proceed.
How to Refer Disputes to Arbitration?
Once the condition precedents if any, are fulfilled and exhausted, the party initiating the arbitration namely the Claimant should refer to the arbitration institution and its prevailing arbitration rules mentioned in the arbitration clause. For the purposes of this article which focuses on construction contract, it is assumed that the parties had agreed on an institutional arbitration rather than ad hoc arbitration clause. This is because most construction contracts are based on certain standard forms adopted by the industry which typically include an institutional arbitration clause. Whilst it is common for parties involved in legal action to hire lawyers to drive these arbitration processes, it is still advisable for the disputing parties to have good practical knowledge of the relevant proceedings.
Different arbitration institutions has different expectations as to what is required from the Claimant, in particular how defined and certain should the claims be submitted to the Secretariat or Registrar at the outset. These requirements are usually prescribed in one of the arbitration rules which pertains to Request for Arbitration, Notice of Arbitration etc. There is typically a list of items required from the Claimant that includes amongst others, the arbitration clause, the identity and contact details of the disputing parties, nature of claims including any quantification of damages sought, proposed arbitrator etc. There is usually certain requisite filing fees that shall be paid when arbitration is initiated. The counter party is either copied by email in this initial process or to be notified by the Secretariat once the submissions from the Claimant is deemed complete.
The arbitration institution would typically provide a fee schedule to guide the parties on the relevant costs or deposits that are payable. This fee schedule is usually proportionate to the magnitude of claim or quantum of damages sought. Therefore parties should be as accurate as reasonably possible in its initial quantification of claims. This fee schedule in addition to any legal fees would provide a reality check as to whether such legal action is justifiable and commercially worthwhile.
The Claimant being the party that initiates the arbitral process usually retains the element of surprise. Prior to pulling the trigger, the Claimant, its lawyers or any claims consultants would have discussed, considered and debated over the merit of its case, the strategy including the availability of witnesses or documents to support its case. On the other hand, the Respondent usually does not enjoy the same amount of time as the Claimant in preparing its response or defence including any counter claim. Therefore, as part of the initial process, the Respondent either provide a brief response which usually amount to some form of blanket denial and putting the Claimant to strict proof. Depending on the nature of the claims, the Respondent might reserve its position to mount a counter claim at the later stage to the extent permissible. Therefore, it is clear that whether a party is the Claimant or the Respondent, the ability to achieve the required readiness to engage in the process is an important element that one should be prepared for as early as possible, preferably during the review of any arbitration clause.
How to Review Arbitration Clause Commercially?
Most construction contracts provides for an interim monthly progress payment regime where contractor is paid progressively based on the work done. In other words, the contractor would have to finance the works first before getting paid based on the agreed rates and prices. When parties are in dispute, the progress payments usually get adversely implicated. When the Employer or its consultants rejects the work done on the basis of not being compliant with specification, or the Employer disputes whether certain work done entitles additional payment or for any other reasons, the contractor who finances the work would not get paid until such time when the disputes are resolved and is found to be in the contractor’s favour. This explains why contractors are usually the Claimant in most arbitrations, due to their pursuit for payment, rightly or wrongly. The Employer on the other hand would be financially protected by amongst others, the access to performance bond and being able to make payment only based on work done. Therefore, when one reviews any arbitration clause, it would be useful to first make an educated guess as to whether one is likely to be the Claimant or the Respondent in case of disputes. This assessment will influence the way one decides what elements of the arbitration clause is important or likely to be important. The same dynamic described above equally apply to the relationship between the main contractor and subcontractor.
If one believes that it is likely to be the Claimant, it will be incentivised to resolve the disputes as soon as reasonably possible so as to gain access to the outstanding funds. To this end, the speed at which the proceedings can progress becomes crucial. Thus it is important to understand what are the options available amongst different arbitration institutions based on their prevailing rules. In pursuing speed of dispute resolution, it needs to be balanced with the ability for one to still being able to present its case. It is often a case of trade off. In certain arbitration institutions such as the ICC, the Claimant is expected to be relatively precise and certain with its claims when making a request for arbitration whereas the other institutions merely require a brief statement at the point of notice of arbitration. This is because these other institutions would usually have a separate step for parties to file their statement of claims at a later stage of the proceedings. An arbitral proceeding with clarity and certainty in the scope and issues in dispute can usually progress at a higher pace. It is also quite common for arbitration institutions to offer the option of an expedited procedure to cater to such needs. Any potential Claimant is more likely achieve agreement on an expedited procedure or the choice of arbitration institution that promotes certainty of issues at the outset before any dispute arises. Occasionally parties may agree to opt for proceedings conducted in a memorial style format where statement of claim is filed together with witness statements and expert reports. This format whilst saves considerable time is quite different from the traditional adversarial approach used in common law system where the witness statements and expert reports are filed a later stage after the submissions of statement of claims and statement of defence.
In view of the above it is evident that a good understanding of the mechanics of arbitral proceedings could be beneficial from a commercial perspective. With this understanding in mind, any potential Claimant would be wise to put in place a robust documentation system during the construction duration. This is to facilitate access and retrieval of letters, emails, drawings, or any documents that offers high evidentiary value during any arbitral proceedings. One should be mindful of the fact that personnel and individuals may come and go due to natural attrition and completion of project. Having a robust documentation system can address any such preventable loss of information.
Conclusion
Whilst arbitration is traditionally viewed as a pure legal matter, that cannot be any further from the truth. In reality, most issues in our day to day life are rarely packaged neatly as a pure subject of certain domain knowledge. Issues are usually a complex amalgamation or blend of different domains of knowledge. In case of arbitration provisions, it pays to appreciate its underlying commercial value despite the common perception of it being a pure legal matter.
Koon Tak Hong Consulting Private Limited
