This article compares valuation of variations mechanism included under two of the more commonly used standard conditions of construction contract in Malaysia namely Agreement and Conditions of ‘Pertubuhan Akitek Malaysia’ (PAM) 2018 and Standard Form of Contract of ‘Jabatan Kerja Raya’ (JKR) or Public Works Department (PWD) Rev 2007 Form 203A. This is Part 5 of an article series comparing various key provisions under PAM and JKR contracts.
Variation is a common subject of dispute under construction contract in particular how it should be valued. This is quite surprising considering the fact that valuation of variation clauses under contract forms are some of the more detailed and structured provisions as compared to clauses governing other subjects. One possible reason is that those from legal background responsible for drafting these clauses and those from quantity surveying background valuing variations on a regular basis may not share the same view point. When examining valuation of variation clauses in subsequent sections of this article, it will be clear that there are various aspects of these provisions that are open to different interpretations. In fact both PAM and JKR contracts have quite different approaches to valuation of variations. Therefore this article helps to highlight some challenges when interpreting these clauses including the need to value variations differently in accordance with contract forms used.
By way of background, there is a similar article published in this website entitled ‘Part 3 of SIA vs PSSCOC – How To Value Variations?’ that that makes similar comparison but based on contract forms used in Singapore. It is interesting to note that there are significant similarities between Singapore and Malaysia concerning valuation of variations. One of the similarities relates to the general rules of valuation of variations which is based on a tiered approach which will be expanded further in the next section of this article.
One of the perennial challenge to valuation of variation is determining when to hold the contractor to the end of its bargain by using the agreed unit rates to value variation and when it is not commercially meaningful anymore to do so. When the contractor submits its tender sum, it is an offer that is derived based on a variety of unit rates for the described scope of works. This is particularly so when the tender document includes bills of quantities as its pricing schedule. As with any commercial offer, there are pricing basis and commercial presumption that underpin the tender price e.g. quantities of works, nature of works, duration to carry out the works etc. When an instruction is issued for variation, there is a good chance that these basis and presumption are rendered either partially or wholly inapplicable for the varied works. The overarching principle behind valuation of variation is a balancing act of determining to what extent should the Employer continue to rely on contract unit rates (which are competitive) when variation is instructed. If existing unit rates are not applicable, how should the contractor be meaningfully compensated whilst remaining fair and reasonable to the Employer? What would also be interesting is to find out whether a private sector form of contract (PAM contract) would deal with valuation of variation differently from that of a public sector form of contract (JKR contract)? This may influence tenderers’ pricing strategy when participating in both public and private sector projects. After all the unit rates and prices submitted are not only relevant to the scope of works presented in the tender document but possibly future changes to existing works.
General Rules Of Valuation Of Variations – Tier 1, 2, 3 And 4
The rules on valuation of variations are structured based on a tiered approach ranging from the lowest tier (tier 1) to the highest tier (tier 4). Under tier 1, variation is valued based on contract unit rates whereby the contractor is bound by the unit rates used to derive the accepted tender sum. If the contractor was overly competitive during tender and the contract unit rates were insufficient to compensate for the costs of the varied works, the application of tier 1 may be commercially detrimental to the contractor. In this regard the Employer continues to enjoy competitive rates and pricing even for varied works instructed subsequent to contract formation. Tier 1 is applicable when the varied works instructed is least disruptive to the contractor’s programme for the existing scope of works.
The valuation methodology scales upwards from tier 1 when the varied works instructed becomes increasingly disruptive to the contractor’s programme, thus resulting in progressive departure from the use of contract unit rates to that of compensation by way of cost reimbursement approach. From a commercial perspective, as the valuation methodology evolves from tier 1 to tier 4 it becomes increasingly favourable to the contractor since the contractor is not strictly bound by its unit rates. By contrast the Employer would naturally favour the adoption of tier 1 since it is likely the most cost effective and economical valuation approach. Therefore the interests of both the Employer and contractor are inherently at odds from a valuation of variations perspective. Some have tried using tier 2 and tier 3 as ‘middle ground’ rather than extreme ends of the spectrum. As will be elaborated in subsequent sections of this article, the application of tier 2 and tier 3 can be extremely challenging since these tiers provide either for extrapolation of unit rates (tier 2) or the use of fair market rate (tier 3). How exactly should an original contract rate be arithmetically extrapolated is subjective and how to decide what is considered ‘fair market’ rate can also be contentious. Therefore it is fairly common for disputing parties in legal proceedings to have these valuation issues contested by engaging ‘quantum expert witnesses’.
Although relevant variation clauses tend to be fairly prescriptive in describing which valuation tier is to be used under different circumstances, it continues to be a common source of dispute due to subjectivity in interpretations stemming from the following reasons. Firstly, the nature of changes (or variations) is usually disruptive and the subjectivity lies in agreeing on the degree of disruption. The measure of disruption often relies on comparison against the contractor’s approved baseline programme, method statement for workflow and other post contract deliverable documents, none of which are included as part of the contract document. Therefore it is challenging to establish a neutral measurement of disruption (thus choice of tier of valuation), in the absence of an objective benchmark. Finally, what amounts to disruptive within the context of rules of valuation may also be debatable in the absence of contractual definition. The following sections of this article will provide further detail by examining individual tiers of valuation.
PAM vs JKR – Tier 1
As regards JKR contract, its valuation of variation using tier 1 can be found under Clause 25.1(a). As the procurement pathway of this contract form anticipates the inclusion bills of quantities with provisional quantities, this clause shall be read in conjunction with Clauses 26.6 and 26.7. Both these clauses do not materially affect the application of tier 1 valuation of variation because these are meant to address arithmetical reconciliation arising from remeasurement of actual work done to supersede provisional quantities. Under JKR contract’s tier 1 approach, the rates in the bills of quantities shall be used to determine valuation of work done where such work is of ‘similar character and executed under similar conditions’ as work priced therein.
As alluded to earlier, what type of variation works amount to ‘similar character’ as the existing works can be subjective and be opened to various interpretations. This is because the valuation requirement merely stipulates that the variation work to be of ‘similar’ character rather than being ‘identical’ in character, potentially widening the ambit of this clause. It is unclear whether significant increase in quantity of the very same floor finishes can be considered as ‘similar character’? Alternatively does ‘similar character’ pertains only to physical appearances? These interpretations can be commercially contentious using the following hypothetical example. Let us assume an instruction was issued to change marble floor finishes to that of new type of marble finishes that are similar aesthetics from that of the original marble. However as the new marbles are sourced from further geographical locations, the contractor may dispute the use of same unit rate if it incurs additional transportation or freight costs. Therefore the varying interpretations of Clause 25.1(a) may not provide clarity that is necessary for a completely objective valuation. Additionally, the phrase ‘executed under similar conditions’ can traditionally be benchmarked against the accepted baseline programme. If the variation works were instructed out of sync with such programme, there is arguably a good indication that the varied works should not be valued using tier 1 approach. However, deviations in actual site conditions from baseline programme is part and parcel of construction works. A formal revised programme is not typically requested unless the contract administrator observed material deviation from the approved programme and may request for a revised programme for the contractor to demonstrate that it continues to be able to achieve the original practical completion date. Therefore any tolerable deviations on the programme’s float do not usually warrant the contractor’s submission of a revised programme. In the absence of a revised programme, one may reasonably infer that the varied works did not give rise to any material disruption to the existing workflow. Given the nature of tier 1 valuation of variation, parties ought to rely on other contemporaneous documentations e.g. site diaries, weekly progress reports etc to establish that the varied works may not be executed under similar condition as the original scope of works.
As regards PAM contract (with quantities), its valuation of variation rules are rather unique in that it do not only cater to variation works but also unit rates used for provisional quantities. Under its Clause 11.6, the rules of valuation of variations includes ‘works executed by the contractor for which provisional quantity is included in the contract’ amongst others. This statement is found in the preamble to sub-clauses 11.6(a) to 11.6(f) indicating that the rules of valuation of variation are also applicable under circumstance where the provisional quantities differ significantly from the actual quantities of work executed such that it ‘amounts to variation/ change’. This practice is not found under JKR contract as well as most standard forms of contract as generally deviations from provisional quantity do not amount to variation. ‘Change’ or ‘variation’ is usually applicable if the quantum of existing scope of works is defined and therefore could be compared against. Provisional quantities in and of itself is an indication that the exact quantum of existing scope of works could not be defined. In any case, parties are free to agree on any terms of agreement that fit their requirements, including those relevant conditions found under PAM contract.
As regards tier 1 valuation of PAM contract found under its Clause 11.6(a), the ‘rates and prices’ in the contract document shall be used for valuation where varied works fulfil the following three conditions namely (I) is of a ‘similar character’ to, (II) is executed under ‘similar conditions’ as, and (III) does not significantly change the quantity of work as set out in the contract documents. There are a few notable differences from tier 1 of JKR contract. Firstly, the valuation process under PAM contract could utilise ‘prices’ in addition to unit rates. ‘Prices’ in this regard are discrete lump sum amount found in pricing schedule where the unit of measurement is ‘Item’. This is quite different from unit rates where the unit of measurement is typically dictated by either the preamble of the relevant pricing schedule or standard methods of measurement sanctioned by Royal Institution of Surveyors Malaysia. Since these ‘prices’ are essentially lump sum amounts, it is unclear how these figures can be applied to measured quantities of variation works. Secondly, tier 1 under PAM contract is applicable provided that quantities of varied works do not depart significantly from existing scope of works. This provides further clarity when compared with JKR contract on the scope of tier 1 valuation. Although some may argue that the term ‘significant’ does not completely remove subjectivity, it at least provide certain parameter for the valuer to consider based on the context of the instructed variation works. Apart from these differences, the approach of tier 1 under JKR and PAM contract are similar. Therefore the relevant comments for tier 1 of JKR contract stated above are also applicable to PAM contract.
PAM vs JKR – Tier 2 & 3
As pointed out earlier under PAM contract, all three conditions that had to be fulfilled for tier 1 to be operative. If say condition (II) or condition (III) is not fulfilled then pursuant to its Clause 11.6(b), tier 2 will be applicable. In essence, Clause 11.6(b) states that where work is of a similar character to existing scope of works but is not executed under similar conditions or is executed under similar conditions but there is a significant change in quantity of the variations instructed, the rates and prices in the contract document shall be the ‘basis used for determining the valuation’ which shall include a fair adjustment as appropriate.
There are two important components found under tier 2 namely ‘when’ it is triggered and ‘how’ valuation is carried out upon its trigger. As regards the former, condition (I) shall continue to be fulfilled, i.e. the varied works shall be of ‘similar character’ to the existing scope of works, with either condition (II) or condition (III) remained unfulfilled. As regards the latter, the ‘rates and prices’ in the contract shall be extrapolated by factoring in fair adjustments to account for deviations arising from either condition (II) or condition (III). In order for adjustments to be made effectively, it will be prudent for the parties to agree on the make up of the relevant unit rates and prices through upfront disclosure by the contractor. Without understanding the components within these blended rates, it will be challenging to carry out any arithmetical extrapolations.
What happens if condition (I) cannot be fulfilled i.e. where the works instructed is not of a similar character as the existing scope of works? Under such circumstance, tier 3 under Clause 11.6(c) of PAM contract will be triggered. Given that the varied works is not of a similar character to the existing scope of works, valuation shall be at fair market rates and prices determined by the Quantity Surveyor. Whilst admittedly what is considered ‘fair’ is debatable, there are reasonable amount of publicly available costs data and statistics published by professional bodies and relevant industry associations that may be of assistance. Under tier 3, the contractor not only do not need to be bound by its contract rates and prices, but also have the chance to rely on prevailing rates and prices, which may be months or even a year after the closing of tender. Therefore, tier 3 is of significant commercial advantage to the contractor relative to tier 1 and tier 2, subject to the assessment by the Quantity Surveyor. It is therefore not surprising to find that most commercially astute contractors are more likely to argue that the varied works is not of ‘similar character’ to the existing works when using PAM contract.
As regards JKR contract, its tier 2 is significantly different from that of PAM contract. Under Clause 25.1(b) of JKR contract, the rates shall be the basis of valuation where the instructed works is (I) not of similar character or (II) not executed under similar conditions. As mentioned under tier 1, valuation of variation under JKR contract does not expressly cater to significant difference in quantity. However unlike PAM contract, the contract rates are extrapolated or adjusted as soon as the varied work is not of similar character as the existing scope of works. Where the works are not executed under similar conditions as existing scope of works, much like the PAM contract, tier 2 also is triggered. It is also interesting to note that tier 3 under JKR contract is bundled under the same Clause 25.1(b) where fair valuation shall be applicable as soon as conditions under tier 2 are not fulfilled i.e. the varied works are not of similar character and not executed under similar conditions. Another unique characteristic is that tier 3 under JKR contract is ‘definition by negation’ as opposed to ‘definition by affirmation’. In other words, it is described based on conditions not fulfilled for it to be operative rather than what type of conditions must be fulfilled for it to be operative. Definition by negation tend to be broader in its scope which mean theoretically the contractor should have wider opportunities to utilise fair market rates under JKR contract.
It is important to underscore that whilst tier 3 may be commercially more favourable to the contractor in terms of use of fair market unit rate, this valuation methodology remains distinctly different from compensation by cost reimbursement. By way of illustration, if the Quantity Surveyor determines that fair market rate for certain instructed concrete variation works is RM300/m3, such unit rate is considered a composite unit rate or blended unit rate. It represents costs for all material, labour, plant and equipment necessary for every cubic meter required for the instructed works. Cost reimbursement valuation however is a more generous valuation methodology where the contractor will be reimbursed for its actual resources incurred where each cost component e.g. labourer, material, plant and equipment will be valued separately based on actual level of resources expended. Such methodology can be found under tier 4 which will be further elaborated in the section below.
PAM vs JKR – Tier 4
As mentioned earlier, tier 4 represents reimbursement based on actual resources expended. However there are typically two distinct methods under such tier 4. One usually involves the use of ‘day work rates’ whilst the other uses ‘actual cost’. For ease of discussion we shall refer the former as tier 4.1 and the latter as tier 4.2. What are the differences between tier 4.1 and tier 4.2? It is quite common for certain large projects that require tenderers to submit their daywork rates as part of their proposal. These may include per day or per hour rate of workers with varying skills and experience that are relevant to the project in hand. These daywork rates may also include different types of plant and equipment e.g. tower crane, mobile crane, excavators, concrete mixers etc. For avoidance of doubt, these daywork rates are supplementary to the composite unit rates used to derive the tender sum based on described scope of works. As daywork rates are submitted in advance as part of the tender proposal, tier 4.1 that uses daywork rates has an element of upfront certainty in respect of the costs payable for the anticipated varied works. The contractor however is still required to provide proof of the actual hours or days during which the relevant resources are expended and to produce vouchers or site records for verification purposes. Tier 4.2 on the other hand does not include such daywork rates where the contractor is reimbursed based on prevailing market rates for the relevant resources. Therefore the actual costs incurred by the contractor based on prevailing market rates are reimbursed by the Employer. This is likely because no day work rates were either submitted or available at the point of tender. However, the contractor is still required to produce the same extent of vouchers and site records for similar resource verification purposes. From the contractor’s commercial perspective, tier 4.2 is therefore more favourable than tier 4.1 since it is not bound by any of its rates and prices whatsoever.
Under clause 11.6(d)(i) of PAM contract, tier 4.1 is applicable where tier 1, tier 2 and tier 3 cannot be used to value the varied works. Consequently the contractor shall be allowed to utilise its daywork rates included in the contract document. Where there are no such daywork rates in the contract document and pursuant to Clause 11.6(d)(ii), tier 4.2 will be applicable where the varied works shall be valued in accordance with the actual cost to the contractor of his materials, additional construction plant and scaffolding, transport and labour for the work concerned. There shall also be an additional 15% of relevant costs to account for use of all tools, standing plant, standing scaffolding, supervision, overheads and profit. Further Clause 11.6(d) expressly state that either in case of tier 4.1 or tier 4.2, voucher specifying the time spent daily upon the work, the workers’ names, materials, additional construction plant, scaffolding and transport used shall be signed by the Site Agent and verified by the Site Staff and shall be delivered to the Architect and Quantity Surveyor at weekly intervals with the final records delivered no later than 14 days after completion of varied works.
As regards tier 4 under JKR contract, there are no separate provisions for tier 4.1 and tier 4.2. It appears that JKR only adopts tier 4.1 where if applicable, the variation works shall be valued based on ‘daywork prices’ that are supposed to be specified in the Appendix to the JKR contract conditions. What is peculiar however is that these daywork rates are not typically populated in Appendix to Contract Conditions but instead included in the relevant appendices to pricing schedules. Assuming these daywork prices refer to those populated in a separate pricing schedule e.g. Appendix to Bills of Quantities, then according to Clause 25.2 these shall be taken to mean the actual net cost to the contractor of his materials, plant and labour for the work concerned. In other words, JKR contract appear to combine both tier 4.1 and tier 4.2 where the use of daywork prices is deemed actual costs. Much like the PAM contract, the contractor shall additionally be paid 15% of the relevant cost which shall include the cost of all ordinary plant, tools, scaffolding, supervision and profit. The contractor shall also be required to produce vouchers, receipts and wage books to substantiate the level of actual resources expended within a stipulated time interval.
Conclusion
It is rather apparent that whilst valuation of variation appears to be an objective arithmetical exercise, it can be as vague and subjective as most other contentious issues under construction contract. This is because construction practitioners valuing variations are often required to interpret and construe contract conditions without necessarily appreciating rules of interpretation. It is also clear that valuation of variation should not be viewed as an isolated subject under the contract. It is very much interwoven with other critical provisions such as construction programmes, loss and expense, progress payments etc. This is because the determination of which valuation tier to be used is principally influenced by the extent of disruption to the contractor’s existing works which in turn refers to the approved construction programme. Likewise, resource reimbursement type of valuation approach often overlaps with typical heads of claims under loss and expense, in particular prolongation costs. Therefore valuation of variation provisions are not only relevant to Quantity Surveyors but arguably to practitioners from other disciplines involved in contract administration as well.
Koon Tak Hong Consulting Private Limited
